Detroit BPF Construction!

Detroit Dryer - June 2014

Construction is going well at the Detroit Biosolids Processing Facility and we are running 5 months ahead of schedule.  This is the first of four dryers being set on its trunnions.  The MEC dryer is 13-ft in diameter and 42-feet long.  They took 5 long days to arrive from Neodesha, Kansas on 16 axle trucks that were 130 feet long.  From here structural steel will be going up and the building/roof will be on by winter.  The facility will start operation fall of 2015.